Hello experts,
My business requirement is this:we have 3 maintenance packages in one maintenance strategy :
1 year ,4 year ,8 year ,there corresponding is hierarchies 1 , 2 ,3 .
Business requirement is that smaller hierarchy packages maintenance call completion date offset from its plan date will shift only the sequented maintenance calls with same or lower hierarchies ( for example if 8 year call is completed late then the next 1 year will be shifted as result but if the 1 year will be completed late ,it will not shift the future 8 year call date )
Also it is requires that maintenance Calles for will be released 8 years (full cycle) ahead (the maintenance calls result is notifications)
We where consider the option of develop solution is which will use the work order “save” user exit the next calls ( notifications require start and end fields)
Will be happy to see what solution was implemented for similar requirement.
Thanks in advance
M