Hi,

 

Is there a way to include another "Action" in the BPF.

 

The requirement is :-

 

Planner - Submit the data
Team Lead/Manager - Reviews/Approves the data
Group Planner - Closes the planning cycle

 

However, when the Team Lead/Manager press Approve, the status of BPF step is completed. It is not still open for Group Planner to recheck the numbers and finally close the BPF. If we use Reopen, it will open the BPF for everyone again. How to add another step in "Actions" to Complete and make sure that Approve changes the status to Approved and not completed.

 

Planner is maintained as Owner....Team Lead as Reviewer and Group planner is the Owner of Hierarchy node of base entity.

 

Please advise

 

Regards,
Ab